Westplex Taxilane Reconstruction CMAR

Client

City of Flagstaff

Location

FLAGSTAFF, ARIZONA (FLG AIRPORT)

Delivery

Aviation, CMAR

Cost

$4.58M

Date Completed

August 2014

DESCRIPTION

This project involved the removal and reconstruction of existing taxilanes between and surrounding general aviation hangars in the Westplex area of Flagstaff Pulliam Airport. The existing asphalt pavement was in poor condition, necessitating costly annual maintenance to remain operational.

PRECONSTRUCTION SERVICES

Banicki worked closely with the City of Flagstaff and designer Kimley-Horn to revise the construction phasing and sequencing to reduce project cost and overall duration.

SCOPE

  • 11,000 tons of AC pavement
  • 7,100 CY of ABC
  • 48,800 SY of pavement removal
  • 39,475 SY of subgrade preparation
  • Storm drain systems