North Apron Reconstruction
Client
CITY OF PHOENIX AVIATION DEPARTMENT
Location
LOCATION PHOENIX, ARIZONA (DVT AIRPORT)
Delivery
Aviation
Cost
$6.05M
Date Completed
July 2016
DESCRIPTION
This project involved the complete reconstruction of the north apron area at DVT, featuring a new full-depth asphalt pavement section across the entire 67-acre work area. Long-range planning and daily coordination with DVT tenants, DVT user groups, DVT Operations, and the ATC Tower were critical to ensure smooth execution. Seven construction phases were implemented to minimize disruptions to DVT, enabling Banicki to complete the project in just eight months, two months ahead of schedule.
SCOPE
• 146,016 SY of P-401 AC pavement
• 146,016 SY of P-209 crushed ABC
• 136,530 SY of P-155 lime-treated subgrade
• Utility adjustments
• Electrical adjustments
• Sewer adjustments
• Water valve adjustments
• Aircraft tie-downs